Skip to content
Construction

A five-station tandem press line dismantled, shipped across two seas and recommissioned to original alignment tolerance.

Client
Automotive Tier-1 Manufacturer
Location
Haryana, India → Southeast Asia
Duration
5 months
Material handled
2,150 t
Project summary

Complete relocation of a five-station tandem press line including a 1,600-tonne lead press, transfer automation, die storage and control systems — dismantled, preserved, export-packed, shipped and reassembled at a new facility with commissioning support.

Scope of works

  • Full line survey and match-marking
  • Press dismantling to reassembly tolerance
  • Transfer automation and control system removal
  • VCI preservation and ISPM-15 export crating
  • Multimodal freight and customs coordination
  • Foundation preparation, reassembly and alignment
The challenge

The lead press bed weighed 320 tonnes as a single indivisible component, exceeding the floor loading of the origin facility's only viable extraction route.

The line's control system had been modified extensively over fifteen years with limited documentation, creating a real risk that reassembly would recover mechanical alignment but not functional operation.

The destination foundation was not designed when the project started, and the client's production ramp date could not move.

Our approach

A load-spreading skid route was engineered across the origin floor, distributing the 320 t bed across a temporary steel raft verified against the actual slab construction confirmed by core sampling. The bed was skidded to a hardstand and lifted from there.

Before any disconnection, the control system was surveyed and documented in full — every field connection photographed, labelled and mapped to a reconstructed schematic. That record proved to be the single highest-value deliverable of the project.

Destination foundation design was brought into our scope and completed in parallel with dismantling, with construction running during sea transit. The line went straight from quay to position with no interim storage.

Reassembly was executed to original alignment tolerance with laser survey verification at each station, followed by staged functional testing through to first production part.

Outcome

2,150 t

Components relocated

Zero

Transit damage

Original OEM tolerance

Alignment achieved

None

Interim storage required

Met

Production ramp date

Plant deployed

Equipment mobilised against the engineered method for this programme. Where the correct machine was not in our own fleet, it was brought in rather than substituted.

  • Hydraulic skidding system
  • Climbing jacks and load-spreading rafts
  • 400 t mobile crane
  • SPMT transport modules
  • Laser alignment survey equipment
Site record

Press Line Relocation — India to Southeast Asia — site record 1
Press Line Relocation — India to Southeast Asia — site record 2
Press Line Relocation — India to Southeast Asia — site record 3
Press Line Relocation — India to Southeast Asia — site record 4
Press Line Relocation — India to Southeast Asia — site record 5
Press Line Relocation — India to Southeast Asia — site record 6
Similar scope?

If this looks like your asset, we should talk.

Send us the structure, the environment around it and the date you need it gone. We will come back with a method.